PFI Process Singapore

PFI Process Singapore

The PFI process begins when a building owner receives a BCA Periodic Facade Inspection notice and continues through Competent Person appointment, inspection planning, visual inspection, close-range inspection, findings assessment, reporting and follow-up action.

This page focuses on the step-by-step workflow. For a sample redacted BCA PFI notice with highlighted appointment and report submission deadlines, refer to the BCA PFI Compliance Support page.

IMG 6422 selected scaled
Process

PFI Process at a Glance

8 practical steps from BCA notice to report, repairs and next inspection cycle.

BCA PFI Notice

BCA serves the notice and states the appointment and report deadlines.

Appoint CP

Owner or MCST appoints a Competent Person and submits PFI_F1.

Plan Inspection

CP reviews drawings, records, elevations, access and inspection approach.

100% Visual Survey

Facade is visually inspected using suitable vantage points and drone support where appropriate.

Close-Range Checks

At least 10% close-range inspection per elevation is carried out where required.

Assess Findings

CP assesses defects and decides whether further investigation is needed.

Submit & Repair

CP submits the report or interim report; owner tracks repairs if required.

Repeat Cycle

Maintain records and prepare for the next PFI cycle after 7 years.

The PFI Process Step by Step

A detailed walkthrough of each stage — from the BCA PFI notice and Competent Person appointment to inspection planning, visual and close-range inspection, findings assessment, reporting, repairs and the next inspection cycle.
Step - 1

BCA Serves the PFI Notice

The process usually starts when BCA serves a PFI notice to the building owner. The notice identifies the building, states the inspection requirement and sets out deadlines for CP appointment and report submission.

Do not ignore this step. The notice should be reviewed immediately so the building owner, MCST or managing agent has enough time to appoint the CP, organise access and schedule inspections.

Step - 1
Step - 2

Building Owner Appoints the Competent Person

The building owner appoints the Competent Person to carry out the PFI. The CP leads the technical assessment and may be assisted by Facade Inspector(s) and inspection service providers.

SGFacadeScan supports this stage by reviewing the notice, clarifying the appointment workflow and helping the property team prepare the documents and site information needed for the inspection.

Step - 2
Step - 3

CP Plans the Inspection Approach and Access Method

The inspection plan should consider the facade type, elevation height, access restrictions, resident or tenant impact, site safety requirements, drone feasibility and close-range inspection method.

 

  • Review available architectural drawings, elevation plans and past repair records.
  • Identify facade zones that need visual survey, close-range inspection or further attention.
  • Plan access using drone, rope access, boom lift, gondola or other suitable methods.
  • Coordinate site notices, access routes, security clearance and stakeholder communication.
Step - 3
Step - 4

Carry Out 100% Visual Inspection of the Facade

Visual inspection provides the overall condition record for the facade. Drone-assisted visual survey may be used where suitable to capture high-level photos and videos systematically across the elevations.

The objective is to identify visible defects such as cracks, spalling, staining, delamination, loose elements, failed sealants, damaged cladding, corrosion, water ingress signs and areas requiring closer inspection.

Step - 4
Step - 5

Carry Out Close-Range Inspection

Close-range inspection allows selected areas to be examined up close. The infographic uses the guide of at least 10% close-range inspection per elevation. The actual inspection approach should be planned by the CP based on the latest requirements and site conditions.

Close-range inspection may involve rope access, gondola, boom lift, scaffold or other safe access methods. It is important where tactile assessment, probing, detailed observation or defect confirmation is required.

Step - 5
Step - 6

Assess Findings and Decide the Next Action

After the inspection, the CP reviews the findings and determines whether the building can proceed to reporting with recommended repairs or whether a more detailed facade investigation is needed.


Path A - No Detailed Investigation Needed

If the findings can be addressed through recommended repair works, the report can be prepared and repair recommendations can be communicated to the building owner or MCST.

 

Path B - Detailed Investigation Needed

If the findings suggest more serious or uncertain conditions, an interim report or approval route may be required before carrying out detailed investigation. This should be managed by the CP based on the actual case requirements.

Step - 6
Step - 7

Complete Repairs if Necessary and Keep Records

Where defects are identified, building owners should plan timely repairs and keep proper records. Good records support future maintenance, MCST council updates, budgeting and the next PFI cycle.

  • Keep inspection photos, defect schedules and report records.
  • Document repair scope, contractor details, before-and-after photos and completion dates.
  • Keep communication records for owners, tenants, council members or facility teams.
Step - 7
Step - 8

Step 8 - Repeat the Inspection Cycle

PFI is a periodic regime, so building owners should not treat it as a one-time exercise. After completion, the building should continue to be maintained and records should be kept so the next inspection cycle can be handled more efficiently.

Step - 8
IMG 6319 selected scaled
How do Manage

How SGFacadeScan Manages the Process Manages the Process

Practical support across notice review, inspection planning, site coordination, defect documentation, reporting and post-inspection follow-up.

Process Area

SGFacadeScan Support

Notice to appointment

Review notice, confirm key dates and assist with CP appointment planning.

Inspection planning

Plan access, elevations, drone visual survey and close-range inspection zones.

Site coordination

Coordinate property team, access service providers and inspection schedule.

Defect documentation

Organise photos, locations, severity notes and defect descriptions.

Reporting support

Prepare clear records and reporting inputs for CP review and submission workflow.

Post-inspection follow-up
Support repair planning records and future maintenance documentation.
Resources & FAQs

Frequently Asked Questions

1. What is the first step in the PFI process?

The first step is usually receiving and reviewing the BCA PFI notice. The notice sets out the key deadlines and triggers the CP appointment and inspection planning workflow.

Page 7 focuses on the process workflow. The detailed sample BCA notice belongs on Page 6 because it is mainly a compliance and deadline document.

Inspection access should be planned as soon as the CP appointment and building information are confirmed. Late planning can affect drone availability, rope access scheduling, resident notices and report preparation.

Visual inspection records the overall facade condition, often with photos and videos. Close-range inspection checks selected areas up close where hands-on or tactile assessment may be needed.

The CP assesses the findings and recommends next steps. This may involve repair works, further investigation, records for maintenance or other actions depending on the actual defect condition.

Elevate image one facade at a time

Free Download

PFI Checklist for MCSTs & Building Owners

A practical preparation guide for managing your Periodic Façade Inspection efficiently — reduce delays and plan follow-up actions with confidence.

Prepared by SGFacadeScan Pte. Ltd. — Competent Person-led PFI guidance.

Get the free PFI Checklist

Tell us where to send it and we’ll email a copy plus practical PFI tips for MCSTs and building owners.

We respect your privacy. Your details are used
only to send this checklist and related PFI guidance.